© 2023 by Gracious Dwelling. Proudly created with Wix.com

077142 50823   |   karl_srs@btinternet.com

New Build Cellar Tanking - Sedgley

Working alongside the main contractor who constructed the wider house and chemical supplier the basement covered all three types of waterproofing with an external membrane, waterproof chemicals within the concrete and an internal cavity drain membrane to the walls and floor. 

SRS advised on all aspects of the works however the pouring of the concrete was organised via the main contractor. SRS then installed the external membrane system, internal cavity drainage membranes, floor insulation and submersible pumps within a pre-cast chamber and ran pipework to a pre-agreed location.  

Works: New Build Cellar Tanking.

Location: Sedgley, West Midlands.

Client: Commercial Construction Company.

Date: September 2015.